VERDUN Building at night with transparent LED media facade (conceptual)
Transparent LED Media Facade Proposal

VERDUN, reimagined as a living landmark.

LEYARD ISKY transparent LED installed inside the building, behind the existing blue-tinted glass, facing the street — one synchronized media canvas, six independently controlled zones.

2,250 m²
LED area (prelim.)
6
independent zones
≥75–80%
rated transparency

Conceptual rendering · PRELIMINARY — subject to site survey, mock-up testing, LEYARD quotation and engineering approval

01

Executive Summary

SPARKLINE proposes converting the glazed facades of the VERDUN Building into a synchronized transparent media facade using LEYARD ISKY transparent LED technology, installed indoors behind the existing curtain wall. The recommended Balanced option covers six zones (≈2,247 m² preliminary) with ISKY-N10.4 on the towers and ISKY-N7.8 on the curved podium band. The system preserves daylight and views (manufacturer-rated transparency ≥75–80%; installed transparency to be measured on a mock-up), operates as one canvas or six independent screens, and creates a premium advertising and civic-celebration asset. All figures are preliminary estimates pending survey, LEYARD quotation and regulatory approvals.

VERDUN is a mixed-use tower on a corner roundabout plot: a two-level curved glazed podium with white columns at ground level, three glazed tower volumes rising to approximately L11–L12, white parametric lattice frames on the concave main tower, and cantilevered metallic fins at every slab edge. The curtain wall uses blue-tinted reflective glazing with slab-edge spandrels. These fins, lattices and spandrels are preserved; the LED is set back inside, aligned to vision-glass zones only.

  • 01Indoor installation behind existing glass — no change to the external architecture.
  • 02Existing as-built SLD (LLC-VT-E001) shows a 630 A ATS / MDB — insufficient for the LED connected load; a dedicated new supply is required.
  • 03LEYARD rated operating temperature is 0–40 °C: active ventilation of the glass cavity is a design-critical requirement.
  • 04Blue-tinted glass reduces perceived brightness; daytime advertising visibility must be proven by mock-up.
  • 05Advertising revenue is not guaranteed and depends on municipal advertising licensing.
VERDUN Building photographVERDUN Building photographVERDUN Building photographVERDUN Building photographVERDUN Building photographVERDUN Building photograph
02

Complete Facade Coverage

Select any zone. Dimensions are estimated from photographs and editable — preliminary pending laser survey.

VERDUN original facade
VD-FF-01

Main Front Facade (concave tower)

L03–L11 · Main roundabout, 30–200 m
Display area
648 m²
Model
ISKY-N10.4
Cabinets (2×1 m)
324
Max load
467 kW
Avg load
168 kW
Weight
7,776 kg
Signal
Fiber + redundant loop
Structure
Ceiling-hung aluminium
Installation
Indoor hanging
Maintenance
Interior aisle ≥600 mm

PRELIMINARY — subject to site survey, mock-up testing, LEYARD quotation and engineering approval

03

Architectural Visualizations

Conceptual rendering — built from the actual building photographs.

Original
ORIGINALPROPOSED
04

LEYARD Transparent LED

Specifications verified against the official LEYARD Vteam Isky series datasheet. Prices are indicative, not a quotation.

ISKY-N3.9ISKY-N7.8ISKY-N10.4ISKY-T10.4
Pixel pitch3.9 / 7.8 mm7.9 / 7.8 mm10.4 mm10.4 mm
Rated transparency≥75%≥75%≥80%≥80%
Brightness cd/m²5000–55005000–55005000–55005000–5500
Pixel density /m²32,25616,1289,2169,216
Cabinet resolution502 × 128252 × 128192 × 96192 × 96
Viewing distance>4 m>8 m>10 m>10 m
Weight13 kg/m²13 kg/m²12 kg/m²12 kg/m²
Max power720 W/m²720 W/m²720 W/m²720 W/m²
Avg power260 W/m²260 W/m²260 W/m²260 W/m²
Heat ≈887 BTU/h·m²887 BTU/h·m²887 BTU/h·m²887 BTU/h·m²
IP ratingIP30IP30IP30IP43
Refresh≥1920 Hz≥1920 Hz≥1920 Hz≥1920 Hz
Indicative SAR/m²6,8004,6003,9004,300

Common: cabinet 2000×1000 mm, depth 57 mm (profile box 107 mm), operating 0 °C – 40 °C, AC 100–240 V, 50/60 Hz, lifespan ≥100,000 h, CCC / CE-LVD / CE-EMC / FCC / CB

Blue-tinted glass effect

Effective brightness ≈ LED brightness × glass visible-light transmission (VLT). Blue tint also shifts white point toward blue; content colour calibration is performed through the glass. Effective see-through transparency ≈ LED transparency × glass VLT relative to the existing view. The glass VLT has NOT been provided — values are editable assumptions.

2,000–2,200
effective nit
≈32%
effective see-through (N10.4) vs. open view

Physical mock-up recommended before final product approval.

05

Engineering, Electrical & Control

Preliminary drawings subject to site survey and engineering approval. Existing drawings are references only, not proof of available capacity.

UNFOLDED ELEVATION — LED ZONING (SCHEMATIC)VD-CC-05 · Curved Glass Corner / Podium Band · 304 m²GROUND — COLONNADE (NO LED)VD-LS-0312 m · 324 m²VD-FF-0124 m · 648 m²VD-SF-0218 m · 486 m²VD-RS-0416 m · 432 m²VD-UL-06L02L03L04L05L06L07L08L09L10L11L12 SPARKLINELEYARD ISKY Overall Facade Layout & LED Zoning Plan DWG: SKV-VRD-A-101REV: A (P1) PROJECT: VERDUN BUILDINGSCALE: NTS PRELIMINARY — SUBJECT TO SITE SURVEY & ENGINEERING APPROVAL 1. Zone widths estimated from photographs; verify by laser survey.2. Vision glass height assumed 3.0 m per floor (slab spandrel excluded).3. Fins, lattices and spandrels preserved; LED inside only.4. Each zone independently controllable; all zones frame-synced.

Live load calculation

1,620 kW
Connected load
2,461 A
Current @400 V 3φ
410 kW
Operating load
1,793,610 kWh
Annual energy
538,083 SAR
Annual cost
≈410 kW
Indoor heat

Existing SLD LLC-VT-E001 shows a 630 A ATS (≈415 kVA) — insufficient. A new dedicated supply is required.

Main Supply → LED DBs → Floor DBs → LED PSUs → LEYARD Displays

CMS → Media Servers → Video Processors → Fiber/Network → Floor Controllers → LED Zones

Existing single line diagram
SINGLE LINE DIAGRAM (LLC-VT-E001)
Existing typical floor power
TYPICAL FLOOR POWER

SPIDER.pdf was not received — please provide it.

06

Installation Methodology

Animated installation sequence
EXTERIORINTERIORGLASSSURVEY
01
Site Inspection

Survey every vision-glass bay, slab edge, soffit, ceiling void, riser and electrical room; laser scan facades.

INSTALLATION CROSS-SECTION — EXTERIOR TO INTERIORSLAB ABOVEFLOOR SLABFANEXTERIOREXISTING GLASSVENTILATED CLEARANCELEYARD TRANSPARENT LEDSUPPORTING STRUCTUREMAINTENANCE ACCESSINTERIOR100–150 mm≥ 600 mmservice aislepower / fiber trayOFFICE SPACE☀ SPARKLINELEYARD ISKY Supporting Structure & Installation Cross-Section DWG: SKV-VRD-S-401REV: A (P1) PROJECT: VERDUN BUILDINGSCALE: NTS PRELIMINARY — SUBJECT TO SITE SURVEY & ENGINEERING APPROVAL 1. Cabinet depth 57 mm (profile box 107 mm) — LEYARD.2. Ventilated clearance prevents heat build-up; target cavity ≤40 °C.3. Top hanger to slab soffit; bottom restraint only (no load on glass).
01

Site Inspection

Survey every vision-glass bay, slab edge, soffit, ceiling void, riser and electrical room; laser scan facades.

02

Glass Compatibility Assessment

Measure VLT, reflectance and tint spectrum; test LED visibility through glass at noon and night.

03

Structural Assessment

Verify slab/soffit anchor capacity for 12–13 kg/m² plus frame; pull-out tests.

04

Final Site Measurements

Confirm bay widths, mullion centres and heights; finalise cabinet layout (2000×1000 mm, custom ≤2 m).

05

Supporting Structure Design

Ceiling-hung aluminium frame, 300–500 mm behind glass, with ventilated clearance and service gap.

06

Mounting Bracket Installation

Install top hangers to slab soffit and bottom restraints to floor; level within ±1 mm.

07

Transparent LED Installation

Hang LEYARD ISKY cabinets per manufacturer method (hanging/stacking); align seams to mullions.

08

Electrical Connections

Terminate from floor LED-DBs via RCBO-protected circuits; earth bonding of all frames.

09

Fiber and Signal Connections

Fiber from control room to floor converters; daisy-chain receiving cards with redundant loop.

10

System Programming

Map pixels per zone into one canvas; configure independent and synchronized modes.

11

Display Calibration

Brightness/colour calibration measured from street through the tinted glass; ambient-light schedule.

12

Testing and Commissioning

72-hour burn-in, thermal logging, failover tests, as-built handover.

10 Technical Installation Banners

01
Complete Installation Overview
  1. Survey & mock-up
  2. Structure & brackets
  3. LED hanging
  4. Power & fiber
  5. Calibrate & commission
⚠ Permit-to-work; occupied floors protected.
02
Interior-to-Exterior Installation Section
  1. Glass
  2. Ventilated clearance 100–150 mm
  3. LED plane
  4. Frame
  5. Service aisle ≥600 mm
⚠ No contact between LED and glass.
03
LED Supporting Structure
  1. Soffit anchors
  2. Top hanging beam
  3. Vertical mullions
  4. Bottom restraint
  5. Seismic/anti-sway ties
⚠ Design SF ≥ 2.0; certified anchors.
04
Electrical Distribution
  1. New LED MDB
  2. Riser cable
  3. Floor LED-DB
  4. RCBO circuits
  5. Cabinet PSUs
⚠ LOTO before any work.
05
LED Signal Distribution
  1. Media server
  2. Video processor
  3. Fiber converter
  4. Receiving cards
  5. Redundant loop
⚠ Laser-safe fiber handling.
06
Content Management Architecture
  1. CMS scheduling
  2. Approval workflow
  3. Zone mapping
  4. Proof-of-play
  5. Remote monitoring
⚠ Role-based access; content regulator compliance.
07
Glass Cleaning Procedures
  1. Isolate LED zone
  2. Exterior via BMU/rope access
  3. Interior via service aisle
  4. Neutral pH, lint-free
  5. Inspect & restore
⚠ No liquid spray on LED strips.
08
Preventive Maintenance
  1. Remote diagnostics
  2. Thermal scan
  3. Torque check
  4. Dust removal
  5. Firmware update
⚠ Work at height <2 m only from aisle.
09
LED Module Replacement
  1. Identify via monitoring
  2. Isolate circuit
  3. Unplug LED strip
  4. Insert spare (same batch)
  5. Recalibrate
⚠ ESD wrist strap mandatory.
10
Emergency Maintenance
  1. Alarm received
  2. Emergency isolation (EPO)
  3. Blank content / zone off
  4. Dispatch within 4 h
  5. Root-cause report
⚠ Fire-alarm interface forces all zones OFF.
07

Cleaning & Maintenance

Cleaning & maintenance — realistic walkthrough
Maintenance 1
Loading video
01
Exterior Glass Cleaning

Monthly via existing BMU/rope access; dust-heavy season fortnightly.

Exterior Glass Cleaning

Monthly via existing BMU/rope access; dust-heavy season fortnightly.

Interior Glass Cleaning

Quarterly from service aisle; LED zone switched off and cooled.

Transparent LED Cleaning

Quarterly dry anti-static brush / low-pressure air; never liquids.

Electrical Inspection

Quarterly IR scan of DBs, RCD trip test, earth continuity.

Module Replacement

Hot-swap LED strips from the aisle; same-batch spares.

Power Supply Replacement

Isolate circuit, swap PSU, verify voltage and load.

Video Processor Maintenance

Monthly log review, firmware per LEYARD release, failover test.

Network Maintenance

Fiber loss test annually; switch redundancy test quarterly.

Thermal Inspection

Continuous cavity temperature sensors; alarm at 38 °C, auto-dim/off at 40 °C.

Emergency Repairs

24/7 hotline, 4-hour response, zone isolation from control room.

Daily Monitoring

  • ☐ Remote health dashboard: dead pixels, PSU, receiving cards
  • ☐ Cavity temperature & humidity log
  • ☐ Proof-of-play verification

Weekly Inspection

  • ☐ Visual walk of service aisles
  • ☐ Ventilation fans & filters
  • ☐ Street-side visual check day & night

Monthly Maintenance

  • ☐ Exterior glass clean
  • ☐ Processor/server log review
  • ☐ Backup & content archive

Quarterly Preventive

  • ☐ Interior glass & LED dust removal
  • ☐ IR thermography of DBs
  • ☐ Failover and UPS tests

Annual Plan

  • ☐ Full colour re-calibration
  • ☐ Structural fixings torque audit
  • ☐ Fiber OTDR test, firmware upgrade

Five-Year Strategy

  • ☐ Replenish spares from same batch (yr 3)
  • ☐ Media server refresh (yr 4–5)
  • ☐ Performance audit vs. original brightness

Recommended spares

  • • LED strips/modules: 3% of installed quantity, same production batch
  • • Power supplies: 5% of installed quantity
  • • Receiving cards: 5%; sending cards: 1 per processor
  • • Fiber converters/SFPs: 2 per floor
  • • Ventilation fans & filters: 10%
07·B

Control Room, CMS & Backup

A compact on-site control room beside the content management system, with full redundancy so the facade never goes dark. Preliminary sizing — subject to design.

Facade control room concept
Conceptual rendering
Live failover simulation
CMS (cloud)Fibre + 5GServer AServer BProcessors ×2Floors L03… L11LED zonesNAS RAID-6UPS 10 kVAGeneratorNORMAL — A active, B hot standby

Control room

  • • ≈ 12–16 m² room, Level 1 or basement, near main LED DB riser
  • • 2 operator desks, 4×27" monitors, 2×2 55" preview video wall
  • • 42U rack: media servers, video processors, core switch, NAS
  • • Dedicated split A/C (N+1), raised access floor, FM-200 or clean-agent suppression
  • • Access control + CCTV covering facade and room

Content management system

  • • Playlist & daypart scheduling per zone (VD-FF-01…VD-UL-06)
  • • Event/takeover mode: one click syncs all zones
  • • Auto-brightness from ambient light sensor + curfew dimming
  • • Proof-of-play logs for advertisers and municipality
  • • Remote monitoring: module, PSU, temperature and fan alarms by SMS/email
  • • Role-based approval workflow (content → legal → publish)

Backup & redundancy

  • • Media servers A + B in hot standby — auto-failover < 2 s
  • • Dual sending cards + loop-back (ring) data cabling per floor
  • • Online UPS 10 kVA, 30 min for control room & processors
  • • Backup generator / ATS for control circuits (LED load sheds first)
  • • NAS RAID-6 content library + nightly off-site cloud copy
  • • Dual internet: fibre primary + 5G failover for remote CMS
  • • Safe-mode loop stored locally on processors if all servers fail
08

Cinematic Media Scenarios

Conceptual rendering

Saudi National Day
Loading video
F1 / 6
Dark → green sunrise sweeps L03→L11
Daytime
Daytime — limited visibility
Main facade
Main facade view

Saudi National Day

Saudi green, palm & swords emblem, Najdi geometry flowing in sync across all zones.

Duration: 90 s loop, 18:00–02:00, 23 Sept week

  1. F1Dark → green sunrise sweeps L03→L11
  2. F2“عزّنا بطبعنا” rises on the towers; slogans run along the podium
  3. F3Emblem reveal on main facade
  4. F4Building-wide pulse finale
  5. F5Crown Prince Mohammed bin Salman — cinematic hero across the main towers
  6. F6Leadership tribute: King Salman & Crown Prince Mohammed bin Salman on the main towers
VD-FF-01Emblem & hero
VD-SF-02Patterns
VD-CC-05Running motif band
09

Detailed Bill of Quantities

Balanced (Recommended) · yellow cells are editable · PRELIMINARY — subject to site survey, mock-up testing, LEYARD quotation and engineering approval

#DescriptionManufacturerModelSpecificationUnitQtyUnit SARTotal SARRemarksStatus
VD-FF-01.01LEYARD transparent LED display – Main Front Facade (concave tower)LEYARD VteamISKY-N10.4P10.4 mm, ≥80% rated transparency, 5000–5500 cd/m², 192 × 96 px/cabinetm²2,527,200324 cabinets 2000×1000 mm; indoor behind glassEstimate
VD-FF-01.02Ceiling-hung aluminium supporting frame, brackets & anchorsSPARKLINE (local fab.)AL-6063-T5Designed for 12 kg/m² + safety factor 2.0m²421,200Slab/soffit anchor capacity to be verifiedTBC
VD-FF-01.03LED power supplies & cabinet power harnessLEYARD VteamPer datasheetAC 100–240 V inputNo.58,320Confirm if integrated in cabinet priceTBC
VD-FF-01.04Floor LED distribution boards, MCB/RCBO, SPD, cabling, earthingSchneider / ABB (or equal)LED-FDBConnected load 466.6 kW (720 W/m² max)kW513,260Supply capacity NOT confirmed by existing SLDEstimate
VD-FF-01.05Fiber backbone, receiving cards distribution & signal cablingCorning / CommScope (or equal)OM4 / OS2Redundant fiber loop per zoneLot70,920Route via existing risers – surveyEstimate
VD-FF-01.06Installation accessories, fixings, cable traysVarious—Stainless/zinc-platedm²77,760—Estimate
VD-FF-01.07Installation labour (structure, LED, terminations)SPARKLINE—Night/weekend works in occupied floorsm²356,400—Estimate
VD-SF-02.01LEYARD transparent LED display – Secondary Front Facade (central finned tower)LEYARD VteamISKY-N10.4P10.4 mm, ≥80% rated transparency, 5000–5500 cd/m², 192 × 96 px/cabinetm²1,895,400243 cabinets 2000×1000 mm; indoor behind glassEstimate
VD-SF-02.02Ceiling-hung aluminium supporting frame, brackets & anchorsSPARKLINE (local fab.)AL-6063-T5Designed for 12 kg/m² + safety factor 2.0m²315,900Slab/soffit anchor capacity to be verifiedTBC
VD-SF-02.03LED power supplies & cabinet power harnessLEYARD VteamPer datasheetAC 100–240 V inputNo.43,740Confirm if integrated in cabinet priceTBC
VD-SF-02.04Floor LED distribution boards, MCB/RCBO, SPD, cabling, earthingSchneider / ABB (or equal)LED-FDBConnected load 349.9 kW (720 W/m² max)kW384,890Supply capacity NOT confirmed by existing SLDEstimate
VD-SF-02.05Fiber backbone, receiving cards distribution & signal cablingCorning / CommScope (or equal)OM4 / OS2Redundant fiber loop per zoneLot64,440Route via existing risers – surveyEstimate
VD-SF-02.06Installation accessories, fixings, cable traysVarious—Stainless/zinc-platedm²58,320—Estimate
VD-SF-02.07Installation labour (structure, LED, terminations)SPARKLINE—Night/weekend works in occupied floorsm²267,300—Estimate
VD-LS-03.01LEYARD transparent LED display – Left Side Facade (finned wing)LEYARD VteamISKY-N10.4P10.4 mm, ≥80% rated transparency, 5000–5500 cd/m², 192 × 96 px/cabinetm²1,263,600162 cabinets 2000×1000 mm; indoor behind glassEstimate
VD-LS-03.02Ceiling-hung aluminium supporting frame, brackets & anchorsSPARKLINE (local fab.)AL-6063-T5Designed for 12 kg/m² + safety factor 2.0m²210,600Slab/soffit anchor capacity to be verifiedTBC
VD-LS-03.03LED power supplies & cabinet power harnessLEYARD VteamPer datasheetAC 100–240 V inputNo.29,160Confirm if integrated in cabinet priceTBC
VD-LS-03.04Floor LED distribution boards, MCB/RCBO, SPD, cabling, earthingSchneider / ABB (or equal)LED-FDBConnected load 233.3 kW (720 W/m² max)kW256,630Supply capacity NOT confirmed by existing SLDEstimate
VD-LS-03.05Fiber backbone, receiving cards distribution & signal cablingCorning / CommScope (or equal)OM4 / OS2Redundant fiber loop per zoneLot57,960Route via existing risers – surveyEstimate
VD-LS-03.06Installation accessories, fixings, cable traysVarious—Stainless/zinc-platedm²38,880—Estimate
VD-LS-03.07Installation labour (structure, LED, terminations)SPARKLINE—Night/weekend works in occupied floorsm²178,200—Estimate
VD-RS-04.01LEYARD transparent LED display – Right Side Facade (east tower)LEYARD VteamISKY-N10.4P10.4 mm, ≥80% rated transparency, 5000–5500 cd/m², 192 × 96 px/cabinetm²1,684,800216 cabinets 2000×1000 mm; indoor behind glassEstimate
VD-RS-04.02Ceiling-hung aluminium supporting frame, brackets & anchorsSPARKLINE (local fab.)AL-6063-T5Designed for 12 kg/m² + safety factor 2.0m²280,800Slab/soffit anchor capacity to be verifiedTBC
VD-RS-04.03LED power supplies & cabinet power harnessLEYARD VteamPer datasheetAC 100–240 V inputNo.38,880Confirm if integrated in cabinet priceTBC
VD-RS-04.04Floor LED distribution boards, MCB/RCBO, SPD, cabling, earthingSchneider / ABB (or equal)LED-FDBConnected load 311 kW (720 W/m² max)kW342,100Supply capacity NOT confirmed by existing SLDEstimate
VD-RS-04.05Fiber backbone, receiving cards distribution & signal cablingCorning / CommScope (or equal)OM4 / OS2Redundant fiber loop per zoneLot62,280Route via existing risers – surveyEstimate
VD-RS-04.06Installation accessories, fixings, cable traysVarious—Stainless/zinc-platedm²51,840—Estimate
VD-RS-04.07Installation labour (structure, LED, terminations)SPARKLINE—Night/weekend works in occupied floorsm²237,600—Estimate
VD-CC-05.01LEYARD transparent LED display – Curved Glass Corner / Podium BandLEYARD VteamISKY-N7.8P7.9 / 7.8 mm, ≥75% rated transparency, 5000–5500 cd/m², 252 × 128 px/cabinetm²1,398,400152 cabinets 2000×1000 mm; indoor behind glassEstimate
VD-CC-05.02Ceiling-hung aluminium supporting frame, brackets & anchorsSPARKLINE (local fab.)AL-6063-T5Designed for 13 kg/m² + safety factor 2.0m²197,600Slab/soffit anchor capacity to be verifiedTBC
VD-CC-05.03LED power supplies & cabinet power harnessLEYARD VteamPer datasheetAC 100–240 V inputNo.27,360Confirm if integrated in cabinet priceTBC
VD-CC-05.04Floor LED distribution boards, MCB/RCBO, SPD, cabling, earthingSchneider / ABB (or equal)LED-FDBConnected load 218.9 kW (720 W/m² max)kW240,790Supply capacity NOT confirmed by existing SLDEstimate
VD-CC-05.05Fiber backbone, receiving cards distribution & signal cablingCorning / CommScope (or equal)OM4 / OS2Redundant fiber loop per zoneLot57,160Route via existing risers – surveyEstimate
VD-CC-05.06Installation accessories, fixings, cable traysVarious—Stainless/zinc-platedm²36,480—Estimate
VD-CC-05.07Installation labour (structure, LED, terminations)SPARKLINE—Night/weekend works in occupied floorsm²167,200—Estimate
VD-UL-06.01LEYARD transparent LED display – Upper-Level Crown GlassLEYARD VteamISKY-N10.4P10.4 mm, ≥80% rated transparency, 5000–5500 cd/m², 192 × 96 px/cabinetm²218,40028 cabinets 2000×1000 mm; indoor behind glassEstimate
VD-UL-06.02Ceiling-hung aluminium supporting frame, brackets & anchorsSPARKLINE (local fab.)AL-6063-T5Designed for 12 kg/m² + safety factor 2.0m²36,400Slab/soffit anchor capacity to be verifiedTBC
VD-UL-06.03LED power supplies & cabinet power harnessLEYARD VteamPer datasheetAC 100–240 V inputNo.5,040Confirm if integrated in cabinet priceTBC
VD-UL-06.04Floor LED distribution boards, MCB/RCBO, SPD, cabling, earthingSchneider / ABB (or equal)LED-FDBConnected load 40.3 kW (720 W/m² max)kW44,330Supply capacity NOT confirmed by existing SLDEstimate
VD-UL-06.05Fiber backbone, receiving cards distribution & signal cablingCorning / CommScope (or equal)OM4 / OS2Redundant fiber loop per zoneLot47,240Route via existing risers – surveyEstimate
VD-UL-06.06Installation accessories, fixings, cable traysVarious—Stainless/zinc-platedm²6,720—Estimate
VD-UL-06.07Installation labour (structure, LED, terminations)SPARKLINE—Night/weekend works in occupied floorsm²30,800—Estimate
PRJ.01Video processors / sending controllers (incl. 1 hot-standby)LEYARD-approvedTBC by LEYARDFrame-locked multi-zone syncNo.595,000Model per LEYARD system designTBC
PRJ.02Media servers, redundant pair (N+1)TBC4K multi-outputGenlock, 24/7 dutyNo.320,000—Estimate
PRJ.03Content management software & scheduling licenceTBCEnterprise CMSRemote monitoring, proof-of-playLot180,000—Estimate
PRJ.04Core network switches, firewall, UPS for control roomCisco / Aruba (or equal)—Dual-ring redundancyLot220,000—Estimate
PRJ.05Engineering, design, structural & electrical calculationsSPARKLINE—4% of equipmentLot367,612—Estimate
PRJ.06Mock-up, testing & commissioningSPARKLINE / LEYARD—1.5% of equipmentLot137,855Physical mock-up mandatoryEstimate
PRJ.07Spare parts (LED strips, PSUs, receiving cards)LEYARD Vteam—3% of LED valueLot269,634Same production batchEstimate
PRJ.08Shipping, customs, insurance, site logistics——2.5% of equipmentLot229,758—Estimate
PRJ.09Regulatory approvals (municipality, civil defence, advertising licence)——Fees & consultancyLot150,000Prerequisite to operationTBC
Subtotal 16,772,159 · Contingency 1,677,216 · VAT 2,767,406 · TOTAL 21,216,781 SAR
10

CAPEX & OPEX

PRELIMINARY — subject to site survey, mock-up testing, LEYARD quotation and engineering approval

SAREconomyBalanced (Recommended)Premium
LED area m²1,4382,2502,250
Equipment6,577,62010,285,30012,299,500
Installation963,4601,507,5001,507,500
Structures934,7001,462,5001,462,500
Electrical1,138,9401,782,0001,782,000
Network412,520580,000580,000
Engineering379,505517,612598,180
Logistics143,441229,758280,113
Testing254,310407,489498,128
Contingency1,080,4501,677,2161,900,792
VAT1,782,7422,767,4063,136,307
TOTAL CAPEX13,667,68821,216,78124,045,020
Electricity / yr343,895538,083538,083
Maintenance / yr164,441257,133307,488
11

Five-Year Revenue & ROI

Illustrative estimates — revenue is not guaranteed. Municipal advertising approval is a prerequisite.

Revenue linked to major Saudi events

Full-facade takeover packages during events, added on top of slot sales. Days × day rate × sell-through. Dates per public announcements — verify before contracting. Event marks require official licensing.

EventSAR/daySell %20272028202920302031
·····
1.9M
····
1.8M
1.8M
1.8M
1.8M
1.8M
··
0.7M
2.1M
2.0M
·····
1.5M
1.5M
1.5M
1.5M
1.5M
0.3M
0.3M
0.3M
0.3M
0.3M
0.2M
0.2M
0.2M
0.2M
0.2M
0.7M
0.7M
0.7M
0.7M
0.7M
Total event revenue6.4M4.5M5.2M6.6M6.5M

World Cup 2034 and Asian Games 2034 fall outside this 5-year window — switch to 10 yrs to see their impact.

21.22M
CAPEX
12.98M
Y1 revenue
163%
5-yr ROI
29.2M
Event revenue
2.22 yrs
Payback
SAR20272028202920302031
Revenue12,980,24013,309,39515,353,50117,155,32117,533,414
Energy538,083548,845559,822571,018582,438
Maintenance257,133257,133257,133257,133257,133
Software250,000250,000250,000250,000250,000
Commission1,947,0361,996,4092,303,0252,573,2982,630,012
Content/insurance750,000750,000750,000750,000750,000
Annual OPEX3,742,2523,802,3874,119,9804,401,4494,469,583
Net cash flow9,237,9889,507,00811,233,52112,753,87213,063,831
Cumulative9,237,98818,744,99629,978,51742,732,38955,796,220
Return on CAPEX %4445536062
Revenue vs OPEX vs Net
Cumulative cash flow − CAPEX (payback)
5-yr ROI by scenario
Sensitivity: 5-yr ROI vs rate & occupancy

Net = Revenue − OPEX · Return = Net ÷ CAPEX × 100 · 5-yr ROI = (Cumulative − CAPEX) ÷ CAPEX × 100 · Payback from cumulative cash flow.

Editable 5-yr ROI — Excel
12

Risks & Implementation

high
Glass Compatibility
Measure VLT/reflectance; mock-up on worst-case bay.
medium
Structural Loads
12–13 kg/m² + frame; soffit pull-out tests; structural engineer sign-off.
high
Solar Heat Gain
Cavity may exceed 40 °C on sun-facing facades; forced ventilation and thermal sensors.
high
Thermal Management
Link to HVAC; auto-dim/shutdown; ~0.26 kW/m² dissipated indoors.
high
Daytime Visibility
5,000–5,500 nit before glass losses; prioritise night programming; mock-up proof.
medium
Effective Transparency
Rated ≥75–80% ≠ installed; measure on mock-up from interior.
high
Electrical Capacity
Existing 630 A ATS insufficient; new SEC supply / transformer required.
medium
Fire Safety
Civil Defence approval; FA interface; non-combustible frame; sprinkler coverage check.
medium
Maintenance Access
≥600 mm aisle behind LED; tenant coordination for occupied floors.
high
Regulatory Approvals
Municipality building permit and Civil Defence before procurement.
high
Advertising Permissions
Municipal advertising licence is a prerequisite to any revenue.
medium
Roadside Distraction
Brightness limits, no rapid flashing, traffic authority guidance.
low
Equipment Reliability
≥100,000 h lifespan (rated); N+1 servers; spares; warranty terms TBC.
Site Survey
Engineering
Product Verification
Mock-Up Testing
Approvals
Procurement
Electrical Infrastructure
Supporting Structure Installation
LED Installation
System Integration
Testing
Commissioning
Training
Handover
M0M8M16M24M32
  1. 1Adopt the Balanced option as the design basis: ISKY-N10.4 (≥80% rated transparency) on towers, ISKY-N7.8 on the podium band.
  2. 2Build a 2 × 3 m physical mock-up on a south/west bay before final product approval; measure installed transparency, brightness through glass, colour shift and cavity temperature over 14 days.
  3. 3Obtain the official LEYARD quotation, latest datasheet confirmation and warranty terms.
  4. 4Commission an electrical capacity study and apply for a dedicated supply.
  5. 5Secure municipal advertising licence and Civil Defence approval before procurement.

The VERDUN transparent media facade can become one of the region's most recognisable architectural media landmarks while preserving the building's design and interior daylight. The opportunity is commercially attractive under base-case assumptions, but it is gated by four verifications: glass/mock-up performance, thermal behaviour, electrical supply and advertising licensing. SPARKLINE recommends proceeding immediately with Phase 0 — survey, mock-up and approvals — as a low-cost, decision-grade step.